Transformer lead times in 2026: what the data shows, and what 15 makers tell buyers about delivery

We read Wood Mackenzie's lead time data and the websites of 15 transformer and switchgear makers. Power transformers averaged 128 weeks in the second quarter of 2025, and 4 of the 15 makers published a delivery time.

A worker in a hard hat, safety glasses and leather gloves rests a hand on the lid of a gray pole-mount distribution transformer, with rows of identical units on wooden pallets stretching back across a plant bay.
A worker checking finished pole-mount distribution transformers waiting on pallets in a plant's finished-goods bay.

Transformer lead time still runs past two years for the largest units. Power transformers averaged 128 weeks after receipt of order in the second quarter of 2025 and generator step-up units 143 weeks, according to the lead time chart in Wood Mackenzie and American Clean Power’s September 2025 executive summary. Switchgear averaged 44 weeks. The newest figure we could find is secondhand: Reuters reported on July 9, 2026 that Wood Mackenzie’s Ben Boucher put generator step-up lead times past 160 weeks by the first quarter of 2026 (Reuters, via Kitco).

We read the websites of 15 transformer and switchgear makers on Nov. 5, 2026. Four published a delivery time in days, weeks or months, three claimed fast or short lead times without a figure, and eight said nothing about delivery on the pages we read. Only one, JST Power Equipment, published production weeks for each product it builds new. If you can ship in weeks, publish the weeks by product, say how your quotes handle metal prices, and lead with the ratings you can actually build inside the window your buyer has.

What is the transformer lead time in 2026?

Wood Mackenzie’s chart gives average lead times for seven kinds of equipment in the first and second quarters of 2025. Generator step-up and power transformer lead times fell by 4.3 and 10.4 weeks, and switchgear edged down from 47.0 to 44.4. Three-phase pad-mount transformers rose 16.4 weeks to 46.4, and single-phase pad-mounts, reclosers and wire and cable also rose. Wood Mackenzie gave the same averages for generator step-up units, power transformers and switchgear in an Oct. 15, 2025 article on its own site and said tariffs “could well undo any improvements.” We found no public Wood Mackenzie chart for a later quarter.

Fig. 01Average lead times in weeks after order, second quarter of 2025
Average lead times in weeks after order, second quarter of 2025
ItemValue (weeks)Note
Generator step-up transformers143.4 weeks147.7 in Q1 2025
Power transformers128138.4 in Q1 2025
Pad-mount three-phase transformers46.430.0 in Q1 2025
Switchgear44.447.0 in Q1 2025
Pad-mount single-phase transformers2419.9 in Q1 2025
Reclosers22.822.2 in Q1 2025
Wire and cable13.812.4 in Q1 2025

Lead times in weeks after receipt of order. Wood Mackenzie classifies lead times by transformer type, not by voltage or other specifications. Reuters reported on July 9, 2026 that Wood Mackenzie's Ben Boucher put generator step-up lead times above 160 weeks by the first quarter of 2026. Source: Wood Mackenzie and American Clean Power, Making the connection, September 2025, executive summary p. 5.

Distribution transformers, which include the pad-mount units in the chart, are harder to read. Katie Jereza, DOE’s Assistant Secretary for the Office of Electricity, opened a DOE webinar on March 5, 2026 by saying distribution transformer lead times went from three to six months in 2019 to “one to two years or even longer in 2024.” In the same webinar, a Prolec GE speaker said lead times for distribution transformers “have normalized over the last several months,” with delays left in special components such as arresters, secondary breakers and fuses.

High-voltage circuit breaker lead times reached 125 weeks in the second half of 2025, against 77 weeks in 2023, Boucher said in the Reuters story. He said data center construction is driving demand for circuit breakers and switchgear, which “are set to face larger market deficits.”

Why is there a transformer shortage?

Wood Mackenzie’s Aug. 14, 2025 release estimated supply deficits of 30% for power transformers and 10% for distribution transformers in 2025, after demand rose 116% and 41% since 2019. It estimated that imports would supply 80% of US power transformers and 50% of distribution transformers in 2025. The executive summary shows prices from January 2023 to March 2025 up 15% for power transformers, 20% for three-phase pad-mounts, 18% for single-phase pad-mounts and 21% for pole-top units.

POWER magazine’s Jan. 2, 2026 article quoted Patrick Tarver, owner of the transformer brokerage Bolt Electrical, saying “There is not a shortage” and that he could have a standard substation power transformer “delivered within 12 to 14 months” once drawings were approved. The same article, which is secondary reporting, lists capacity coming online, including Virginia Transformer’s $40 million Georgia expansion to raise output by 70% and Eaton’s $340 million three-phase plant in South Carolina.

For a marketer, the shortage changes the sales cycle. Boucher told Reuters that “Equipment availability is becoming the biggest concern for developers,” and the CEO of California’s Roseville Electric Utility told the agency that, with large substation transformers past three years, it now buys equipment for projects it knows are coming five years out. The electrical equipment group ranked second on ISM’s October 2026 growth list, as our ISM breakdown shows. Our durable goods analysis found the industry’s orders for January to September 2026 up 6.5% in dollars but only about 1.7% after price.

What 15 transformer manufacturers and switchgear manufacturers tell buyers about delivery

On Nov. 5, 2026 we read each maker’s homepage and, where they existed, its lead time, FAQ, shipping and main product category pages.

Fig. 02What 15 transformer and switchgear makers' websites say about delivery
MakerWhat it sellsDelivery language found
JST Power EquipmentNew transformers, switchgear, breakersProduction weeks by product: power transformers 46, cast resin 30, pad mount 30, VPI 26, gas-insulated switchgear 30, gas-insulated RMU 26, outdoor substation breaker 16, dead tank substation breaker 30; quote and drawing weeks listed separately
Maddox TransformerStock, new and remanufactured unitsStock units delivered within 3 to 5 business days; quotes in 30 minutes
Marcus TransformerStock and custom transformersCustom unit delivered within 7 days of request
Jordan TransformerRemanufactured power transformersRemanufactured unit delivered in 15 months
Virginia TransformerNew transformersShortest lead times in the industry; no figure
Giga EnergyTransformers, switchboards, substationsFast lead times on in-stock and made-to-order units; no standard figure (a customer quote cites a 7-week turnaround)
OlsunDry-type transformersQuick-turn standard units; no figure
ERMCO, Hammond Power Solutions, IEM, Meta Power Solutions, Myers Power Products, PCX, Pioneer Power Solutions, Trayer EngineeringTransformers, switchgear or bothNone found on the pages read

Homepages plus lead time, FAQ, shipping and main product category pages where they existed. Wording paraphrased; quotes in the text are exact. Source: Our read of 15 makers' websites, Nov. 5, 2026.

JST Power Equipment’s products page is the most useful page we read. It lists production weeks for eight products, power transformers at 46 weeks and an outdoor substation breaker at 16, with separate columns for quote time (one to six weeks) and drawings (two to eight weeks). A footnote reads “Production lead times only” and sends buyers to the team for complete project lead times.

The other three numbers come from narrower businesses. Maddox Transformer’s shipping policy says stock units “deliver within 3-5 business days,” and its homepage promises quotes in 30 minutes; Maddox sells from stock, including remanufactured units. Marcus Transformer says it will “design, manufacture and deliver your custom-made transformer within 7 days of your request.” Jordan Transformer remanufactures power transformers and asks, “How does JT deliver your unit in 15 months?”

Virginia Transformer’s lead time page claims “the shortest lead times anywhere in the industry,” with a footnote that “Lead times may vary.” Giga Energy offers “Fast lead times on in-stock inventory & made-to-order options,” and a customer quote on its homepage cites “Giga’s 7-week turnaround” on one project. Olsun offers “quick-turn standard units.” None of the three publishes a standard lead time. Two claims we recorded at our first pass on Nov. 3 were gone by Nov. 5: the 16 to 18 week figure on Meta Power Solutions’ homepage, and Giga’s “industry-best lead times,” which now reads “fast lead times.”

Virginia Transformer’s index pricing page ties a quote to an index of its input costs (copper, aluminum, steel, core steel, oil, components, labor and overhead) plus a profit factor, dividing the shipment month’s factor by the quote month’s. The factors run against a December baseline and reach 1.132 for July, which would put a unit quoted in December and shipped in July about 13% above its quoted price. The page’s own label on that table reads “The Index uses December 2026 as a baseline,” and a second table runs from December 2025 to June 2026.

How a smaller electrical equipment maker should sell during the shortage

JST lists production weeks by product family on one page, with quote and drawing time in their own columns. Copy that layout so nobody reads your 16 weeks as door to door. Put the date at the top and update it monthly so a buyer knows how current the figure is.

Virginia Transformer’s index page is the model for anyone who quotes against an index, with the index, its monthly factors and the baseline month all public, and our price increase letter guide covers how to word a surcharge or index clause. If you hold firm prices for a period instead, say for how long.

If your shop can build pad-mounts under 2,500 kVA inside your buyer’s window and is slow on anything above, put the fast products at the top of the quote form and the lead time page, and give your reps and distributors the same table, since they field the “when can I have it” call first.

Owners on data center projects often buy switchgear and transformers themselves, which our data center supplier guide covers, so the lead time page has to work for them too. Add the lead time page and your index terms to your 2027 marketing plan as early projects, and check Wood Mackenzie’s next public update before you set any industry figure beside your own.

Sources

  1. Wood Mackenzie and American Clean Power, Making the connection: Meeting the electric T&D supply chain challenge, executive summary, September 2025 (PDF hosted by POWER)
  2. Wood Mackenzie, Mind the gap: tackling supply-chain challenges in the electric T&D sector, Oct. 15, 2025
  3. Wood Mackenzie, Power transformers and distribution transformers will face supply deficits of 30% and 10% in 2025, Aug. 14, 2025
  4. Reuters via Kitco, US power companies scramble to secure equipment as surging data center demand strains supplies, July 9, 2026
  5. US Department of Energy, Distribution Transformer Convening Webinar transcript, March 5, 2026
  6. POWER magazine, Transformers in 2026: Shortage, Scramble, or Self-Inflicted Crisis?, Jan. 2, 2026
  7. JST Power Equipment, Products and Services
  8. Maddox Transformer homepage
  9. Maddox Transformer shipping policy
  10. Maddox Transformer FAQ
  11. Marcus Transformer homepage
  12. Jordan Transformer homepage
  13. Virginia Transformer, Shortest lead times
  14. Virginia Transformer homepage
  15. Virginia Transformer, Index Pricing
  16. Giga Energy homepage
  17. Meta Power Solutions homepage
  18. Meta Power Solutions FAQ
  19. Meta Power Solutions, Three-phase pad mount transformers
  20. Meta Power Solutions, Single-phase pad mount transformers
  21. Meta Power Solutions, Substation transformers
  22. ERMCO homepage
  23. Pioneer Power Solutions homepage
  24. Olsun homepage
  25. IEM homepage
  26. Myers Power Products homepage
  27. Hammond Power Solutions homepage
  28. Hammond Power Solutions, General FAQ
  29. Trayer Engineering homepage
  30. PCX homepage
  31. PCX FAQ

See an error? Email editor@planttopipeline.com with what is wrong. We fix errors and log them on the corrections page.

Filed under

Filed under

The Tuesday issue

One idea, one number and one example from a company like yours. Every Tuesday, under five minutes.

We use your email to send our newsletter and marketing emails. Unsubscribe anytime. Read our privacy policy.