Industry edition · Customer and Aftermarket
Your customer's supplier scorecard can decide whether you get the next RFQ
Seven of 11 customers' supplier scorecards tie the rating to new business, so a shop that knows each formula can plan the account around it.

Astemo Americas rates the direct-material suppliers of six plants in Kentucky and Georgia over each April-to-March fiscal year, and its supplier rating section says a supplier scoring below 70% “May be ineligible for new business opportunity” and “May be ineligible for RFQ’s (buyer’s option).” A machine shop or stamper that falls below that line at Astemo may not be asked to quote, at the buyer’s option. The key account plan template at the end of this piece starts from that kind of rule in each customer’s scorecard.
We read the public scorecards of 11 OEMs and large tier suppliers that buy machined, fabricated, stamped and cast parts: six in trucks, trailers and auto parts, four in aerospace and defense, and a sensor maker. Seven say in writing that the rating affects new business, quoting or bid lists, source selection or new orders. The formulas differ in other ways, since three count an early delivery against the supplier, four score price or cost savings, and four take points for slow answers to corrective action requests. Our guide to growing the OEM accounts you already have puts the scorecard on the quarterly review agenda as one row of an account map, and the template here fills in that row.
Seven of the 11 tie the rating to the next piece of work
Five documents say what a named rating level earns. Jacobs Vehicle Systems’ supplier quality manual, dated January 2023 and posted on Cummins’ website, says “Suppliers that achieve an overall level of ‘Excellent’ or ‘Good’ will have preference of being awarded new business.” General Atomics Aeronautical Systems’ 2019 supplier handbook prioritizes suppliers rated Exceptional, at 98% or better, for “consideration of new business.” Textron Systems’ public rating procedure, dated October 2021, says Green suppliers “will be given every opportunity to quote business opportunities that fall within their capabilities,” while Red suppliers face “additional review before receiving new purchase orders.” On its supplier scorecard page, DRiV (Federal-Mogul Motorparts) says that for suppliers rated Acceptable, 70 to 89, it “will allow new business but the supplier will be at a disadvantage to a ‘Preferred’ supplier,” and Astemo, the fifth, says a supplier scoring below its 70% floor may be ineligible for new business and for RFQs.
PCB Piezotronics and Lockheed Martin Aeronautics state the link without tying it to a level. PCB’s scorecard guidelines call the scorecard “an assessment tool in source selection decisions and supplier approval status,” and Lockheed’s December 2024 memo on its 2025 rating changes says the changes focus on “rewarding performers through formal recognition, bid list inclusion, and strategic collaboration.”
The other four publish formulas or ratings without saying in words that the result affects new business. GE Aerospace’s supplier expectations manual says a supplier that fails to support its capacity and capability checks may get a poor rating and may lose the chance to take part in “future quotations,” which ties the quoting risk to the failure, not the score, so we did not count it. Hendrickson’s supplier performance page gives formulas without saying how the result is used. Nexteer Automotive calls its balanced scorecard “a tool to compare suppliers,” and Great Dane says its scorecards support its “strategic sourcing objectives,” which we read as too general to count.
| Customer | Ties rating to new business | Early delivery counts against you | Cost scored | Corrective-action response time scored | Delivery share of score |
|---|---|---|---|---|---|
| Jacobs Vehicle Systems | Yes | JIT deliveries only | Yes | Yes | 30% |
| Textron Systems | Yes | not stated | No | No | 50% |
| General Atomics Aeronautical | Yes | not stated | No | No | not stated |
| PCB Piezotronics | Yes | not stated | No | Yes | 45% |
| Astemo Americas | Yes | Yes | not stated | not stated | not stated |
| DRiV | Yes | Yes | No | No | 50% |
| Lockheed Martin | Yes | not stated | No | Yes | separate rating |
| GE Aerospace | No | No | Yes | No | not weighted |
| Hendrickson | No | Yes | No | No | 25% |
| Great Dane | No | not stated | Yes | No | 25% |
| Nexteer Automotive | No | not stated | Yes | Yes | 15% |
Public scorecard and rating documents read Nov. 24, 2026. A tie to new business counts only when the document says in words that the rating affects new business, source selection or sourcing decisions, quoting or bid lists, new orders or additional business. Lockheed Martin's tie is in its Aeronautics unit's December 2024 memo on its 2025 rating changes. GE Aerospace links lost quoting chances to failed capacity and capability checks, not to the score, and counts a part received on or before its required date as on time; its composite rating takes the color of the worst of six components. DRiV displays corrective-action responsiveness without scoring it, and GE tracks overdue corrective actions as a reference metric that does not affect the score. Source: Plant to Pipeline review of 11 OEM and tier supplier scorecard documents, Nov. 24, 2026.
On time means a different window at each customer
DRiV counts a line as on time only within “a window of one day early and zero days late to the due date.” Hendrickson marks a shipment early when it arrives more than three days before the PO due date and late when it arrives more than one day after, and says suppliers “are expected to be zero (0) days late”; the extra day is for receiving. Astemo flags each receipt On-Time, Late or Early, “where L or E will equal a negative impact on the score.”
The JVS manual allows more room for just-in-time deliveries, defining on time as “five days prior to the target date to three days after the target date,” though its report card counts a delivery on time “if it is received by the required due date with the correct quantities.” PCB allows three days after the promise date. GE Aerospace counts a part on time if it is “received on or before the Material Requirement Date,” so an early shipment scores as on time there.
DRiV, Hendrickson and Astemo penalize early deliveries and GE does not. Set the ship-date rule in your ERP by customer, against the date that customer measures: the promise date at PCB, the PO due date at Hendrickson, the Material Requirement Date at GE.
| Customer | Earliest that counts | Latest that counts | Measured against |
|---|---|---|---|
| DRiV | 1 day early | 0 days late | Due date, plus or minus 5% of quantity |
| Hendrickson | 3 days early | 1 day late (zero expected) | PO or 9J due date |
| Jacobs Vehicle Systems, JIT deliveries | 5 days early | 3 days late | Target date |
| Jacobs Vehicle Systems, report card | No limit stated | Due date | Required due date, correct quantity |
| PCB Piezotronics | No limit stated | 3 days late | Promise date |
| GE Aerospace | No limit (on or before counts) | 0 days late | Material Requirement Date |
| Astemo Americas | Early lowers the score | Late lowers the score | Due date |
Six of the 11 documents say how the on-time date is applied. Textron Systems, General Atomics Aeronautical, Great Dane and Nexteer measure on-time delivery without stating a window in the text we read, and Lockheed Martin's explainer sets a scheduling rule for partial receipts. Source: Plant to Pipeline review of 11 OEM and tier supplier scorecard documents, Nov. 24, 2026.
Four of the 11 score what you charge
JVS weights cost at 30% of the overall score. It compares three months of invoiced prices with the prior year’s frozen standard cost: a cut of 5% or more scores 5, holding price 3 and a price increase 0. By our arithmetic, a supplier that holds price, delivers on time every time, runs 10 defective parts per million or fewer and has one overdue corrective action scores 4.24, inside the Good band that carries the new-business preference. A price increase takes 0.9 points off and leaves it at 3.34, in Needs Improvement, where JVS may require an action plan.
Nexteer gives 30 of its 100 points to cost savings against a target; its example, 2.27% against 4%, earns 17 points. Great Dane puts 25% on cost, rating items from cost savings initiatives to payment terms on a 0 to 5 scale. GE Aerospace’s Commercial score, according to its July 2024 supplier training deck, compares the productivity projects a supplier executes with a target. If one of these customers is due a 2027 increase, run it through the formula before you send the price increase letter, and time it against the scoring period.
Slow answers to corrective actions cost points at four customers
Lockheed’s April 2021 explainer takes 20 points off a 100-point quality rating for each overdue supplier-responsible corrective action request over the past 12 months. Lockheed Martin Aeronautics’ January 2025 changes cut that to 10 points for each late or rejected response, a deduction its infographic marks “Present Each Month Until Issue Resolves.” At JVS, overdue corrective action responses make up 40% of the quality score, or 16% of the overall score. PCB and Nexteer score the clock in smaller steps: PCB weights the days to close a corrective action at 5%, with full credit at 7 days or fewer and none after 33, and Nexteer subtracts 5 points for each late initial response, root cause or implementation.
DRiV says “SCAR responsiveness does not factor into the supplier’s Overall Score,” but it scores how many corrective action requests a supplier receives, at a quarter of the overall score, as PCB does with its 25% weight on corrective actions per 100 receipts. By our arithmetic on its tables, a supplier with perfect delivery and defects in the 1 to 25 parts-per-million band scores 90, which is Preferred, with one request in a month, and 82.5, which is Acceptable, with two. List every open corrective action in the plan with its due date and an owner.
Some suppliers never see their score
PCB emails scorecards only to Prime Suppliers, “those suppliers who make up 80% of the total spend,” though any supplier “may request their scorecard at any time.” Great Dane says “Only select suppliers will be receiving the scorecards.” Nexteer, Hendrickson, DRiV and GE post scores in supplier portals. Textron and Astemo ask suppliers to report discrepancies, and GE’s training deck tells a supplier that disagrees with its score to raise it with its sourcing contacts. If you have never seen your score at a key account, ask for it, and check the receipts behind it before the period closes.
A key account plan template built on the customer’s scorecard
Keep one page per key account, filled in from the customer’s own document, and update it before each scoring period closes and each quarterly review. It expands the “Your scorecard” row of the OEM account map.
| Section | What goes in it |
|---|---|
| Customer and document | Customer, plant, the scorecard document and revision, where you see the score, and who at the customer owns it |
| Formula | Each category and weight as published, and how the total is built: weighted sum, average or worst color |
| Your score | The last four periods by category, your current level, and the threshold for the next one |
| What the next level earns | The customer’s sentence on new business, quoting or preference, quoted exactly |
| On-time rule | The early and late window, the date measured against, the quantity tolerance, and your ship-date setting for this customer |
| Corrective actions | Each open corrective action request or problem case, its due date and owner, and the response-time points at stake |
| Cost | The customer’s cost or savings target, your result, and any planned price change with its effect on the score |
| Data check | Receipts or rejections you dispute, the evidence and the date raised |
| Points to gain | The one or two categories where the smallest fix moves you up a level, with the arithmetic |
| Review agenda and ask | Score trend, actions closed, and the named part numbers you want to quote next |
| Owner and dates | Who owns the plan, when the scoring period closes, the next review date |
Filled in for the DRiV supplier at 82.5, the “Points to gain” row would say that one fewer corrective action request a month adds 7.5 points and lifts it to Preferred. For the JVS supplier, the cost row would hold the 0.9 points between holding price and raising it. When the review produces an RFQ, our RFQ-to-quote playbook covers turnaround, and our review of OEM purchase terms covers what OEM terms say about customer drawings and data.
How we did this
On Nov. 24, 2026, we read the public scorecard and rating documents of 11 OEMs and large tier suppliers, reopened each URL against our saved copy and recounted each coded item from the source text. A tie to new business counts only when a document says in words that the rating affects new business, source selection or sourcing decisions, quoting or bid lists, new orders or additional business. An early delivery counts against the supplier when the written rule makes it late, non-compliant or a negative on the score. The documents date from May 2019 (General Atomics) to May 2025 (Astemo); four are web pages. Textron Systems’ public procedure is Rev. G; a newer version is marked for internal use only, so we did not use it. We left out a 2018 Stanley Healthcare scorecard guide still posted on Stanley Black & Decker’s supplier portal, because Securitas completed its purchase of Stanley Healthcare from Stanley Black & Decker in July 2022. Documents from General Dynamics Land Systems, Moog, Molex, L3Harris, Apogee and BAE Systems would not open or were blocked. The counts describe only these 11 customers. The full coding (CSV), with the URL and quoted evidence behind every entry, is published with this piece.
Use our data
Free to reuse, including in your own reports and articles, under CC BY 4.0. Please credit Plant to Pipeline and link to this article.
Sources
- Astemo Americas, Section 05, Supplier Rating, Issue 18 (May 22, 2025)
- Jacobs Vehicle Systems, Supplier Quality Manual, Revision 20 (January 2023), hosted on cummins.com
- General Atomics Aeronautical Systems, ASI Supplier Handbook (May 16, 2019)
- Textron Systems, QA-SP48 Rev. G, Supplier Rating System (October 2021)
- DRiV (Federal-Mogul Motorparts), Supplier Scorecard
- PCB Piezotronics, PD2048 Rev B, Supplier Scorecard Guidelines
- GE Aerospace, Supplier Expectations and Performance Management (SEPM) Manual (revised Aug. 28, 2024)
- GE Aerospace, Supplier Rating System training and FAQs (July 2024)
- Lockheed Martin, Supplier Scorecard (revision date April 2021)
- Lockheed Martin Aeronautics, 2025 supplier performance rating enhancements, memo of Dec. 2, 2024, and infographic (January 2025)
- Hendrickson, Quality and Delivery (supplier page)
- Great Dane, Supplier Guide Rev D, Supplier Scorecard
- Nexteer Automotive, Balanced Scorecard, Supplier Users
- Securitas, Securitas completes the acquisition of STANLEY Security (July 22, 2022)
- Plant to Pipeline, manufacturing sales strategy for the OEM accounts you already have
- Plant to Pipeline, how to write a price increase letter or tariff surcharge notice
- Plant to Pipeline, from RFQ to quote: a job shop playbook
- Plant to Pipeline, what OEM purchase terms and AI addendums say about customer drawings
See an error? Email editor@planttopipeline.com with what is wrong. We fix errors and log them on the corrections page.
Filed under
Filed under